Due to extensive changes with the soon available iOS 18 version from Apple, we recommend that you do not install the first version on your IOS devices yet, but wait for the first possible bug fixes and patches. Under certain circumstances, some of your installed apps may encounter problems and not function as usual.
The purpose of this article is to explain how a subcontractor, can report a corrected defect as completed within the TP Quality App, or how you, as a builder or general contractor, can check the reported defect of a subcontractor with the TP Quality App and load the result of your check directly into the project room be able.
Since the procedure for the notification of a defect or rejection by the subcontractor is similar to the review of the notification by the builder or general contractor and only a few selection fields differ here, the following instructions can be used for both processes.
Firstly, select Check:
Next, click on the + on the upper right screen and select Download:
You can add filters to determine which Defects you want to download, or you can keep the settings and load all captured defects.
Select the download symbol on the upper right screen and confirm the download:
You can rearrange the downloaded defects any time by clicking + and choose Filter.
You will now see the list of all defects that are visible to you in the project room under the entered specifications. Tap on a defect from the list to report or reject it.
You then get to the actual interface for the clearance. Here you can see the defect and the various values that were stored during the recording. These values cannot be changed. At the bottom of the screen, tap on the green field with the tick to clear the deficiency or on the red field with the exclamation mark to reject the deficiency notification.
To clear a defect
If you want to clear the defect, tap on the green field with the tick. You can write a comment about the release and take a photo as proof of the clearance. To do this, simply tap in the corresponding fields Comment or Attachment Clearance. When you have added all the attachments you want, save by tapping the green Save button at the bottom of the screen.
To reject a reported defect
If you do not want to reject the displayed defect, tap on the red field with the exclamation mark. You can also add a comment and photos to the rejection. Also, save the rejection once you've added all the attachments you want by tapping the red Save box at the bottom of the screen.
For both the release and rejection, after saving, tap the back arrow in the top left corner when you have finished editing the release.
Note
If you press and hold on a defect from the list , a selection bar with check boxes will unfold on the left side. Select multiple defects at once to either clear them, refuse them all together or delete them from the list, by clicking on the corresponding icons on the bar at the bottom of the screen.
You will now see the list of all imported defects again. All defects that have already been checked are marked green or red on the left, depending on whether you have cleared the defect or rejected it.
If you want to check further Defects proceed as described above. If you have finished checking all concerning defects tap on the + on the upper right screen and select Upload. Confirm the upload and wait for the process to be finished.
Note
You should not upload more than 50 defect clearances at the same time, as this may lead to errors.
You can always check Defects and save the result in the app, even if you have no internet connection, however, the upload to the Thinkproject platform will require an internet connection.
The result of your clearance process is now saved in your project room.
Important
Please update your project data regularly in the app. This is important as any changes made to the project will otherwise not be transferred to your app.
You can update the data for your project by clicking on the sandwich menu at the top left. Then select Manage projects. Next to the relevant project, select the three-dots and click on Update project configuration.
Screenshots are an example. The interface of your platform may look different, but the processes remain the same.